The Mill Resort & Suites Aruba will start Pool Deck
Renovations on May 5th, with an estimated completion date of June 23, 2015
The hotel will keep one of the 2 pools open at a time. The
project will be done in two phases. The first phase, which will include the
completion of the smaller pool area: May 5 - May 22, 2015. The second phase of
the project will include the main pool and the kiddie pool areas: May 26 - June
23, 2015.
Although it is the goal to minimize the impact for guests, there will be 3 to 4 days of heavy drilling
taking place during the first week of the start-up date for each phase. The
hotel will close the areas under construction completely, to allow the use
of the other facilities without any major interruption. The construction
management team is diligently working to minimize inconveniences as we work
hard to maintain these reopening schedules.